Current status |
LA in progress. 4(1) notification published on 30.09.2021. SIA final report published on 30.11.2021. Expert committee report submitted to DC Palakkad. 11(1) notification published on 15.03.2022. Subdivision survey completed. BVR prepared. DVS passed by DC. LA fund sanctioned by KIIFB on 05.08.2022. 19(1) published on 11.10.2022. Entire land taken possession was completed on 27.02.2023.
GAD was approved in 2014. But on 29.03.2023, Railway had directed to revise the GAD by adopting RDSO standard span of 30m. Hence revised final GAD & Alignment submitted to Railways on 17.05.2023. Railway recommended some modification and the same was submitted on 23.01.2024. Awaiting approval of GAD from Railways. The work may be tendered after the approval from Railways. |