General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt)No.942/2017/PWD | 10.07.2017 | 80 | |
District | Thrissur | ||
LAC | Puthukkad |
Project Details | |
---|---|
Actual Start Date | 11.10.2019 |
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 31 |
Railway (km) | 49/100-200 |
Length Including Approaches | 434.70 |
Width of ROB | 10.20 |
GAD Status | Not approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 80 |
Funded By | KIIFB |
Project Outlay(crores) | 34.9 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 1 % | ||
Current status | DPR approved by KIIFB on 28.06.2019 for an amount of Rs.34.9 Cr. LA to be taken up after getting approval of GAD from railways. Railways requested for P&E charges and the amount was released to Railways on 30.05.2022. Revised GAD submitted to Railways on 13.06.2022. Reminder letter sent on 30.06.2022. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line. |