Projects

Nandikkara ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO (Rt)No.942/2017/PWD 10.07.2017 80
District Thrissur
LAC Puthukkad
Project Details
Actual Start Date 11.10.2019
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 31
Railway (km) 49/100-200
Length Including Approaches 434.70
Width of ROB 10.20
GAD Status Not approved
No of Lanes 2
Financial Details
AS Amount(crores) 80
Funded By KIIFB
Project Outlay(crores) 34.9
Work Progress Details
Physical progress 1 %
Current status DPR approved by KIIFB on 28.06.2019 for an amount of Rs.34.9 Cr. LA to be taken up after getting approval of GAD from railways. Railways requested for P&E charges and the amount was released to Railways on 30.05.2022. Revised GAD submitted to Railways on 13.06.2022. Reminder letter sent on 30.06.2022. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line.