LA Requisition submitted to DC on 15.02.2019. AS for LA obtained from Revenue Department as per GO Rt. 3387/2019/RD dt 06.11.2019. 4(1) Notification published on 17.02.2021. SIA public hearing conducted on 06.07.2021. 11(1) Notification published on 23.10.2021. As per the letter No.D1-124/2021 dtd. 07.06.2022 the Special Tahsildar (LA) Kiifb informed that 5 survey numbers were not included in the requisition. Hence RBDCK submitted revised requisition and alignment sketch to District collector and LAO on 08.06.2022. As per letter No.REV/B1/821/2019-REV dtd. 27.06.2022 of Revenue Dept. informed that "it is requested to issue draft addendum 11(1) notification by incorporating the additional acquisition. Additional survey numbers are to be added in 11(1) as addendum and draft 11(1) preparation is under progress by LAO. Approximate LA cost of Rs. 40 Cr released to LAO on 19.08.2022. 19(1) declaration to be published by LAO.
GAD approved by Railways on 30.01.2023. |