General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt) No. 942/2017/PWD | 10.07.2017 | 50 | |
District | Kollam | ||
LAC | Eravipuram |
Project Details | |
---|---|
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 77 |
Railway (km) | 151/300-400 |
Length Including Approaches | 387.60 |
Width of ROB | 10.20 |
GAD Status | Not approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 50 |
Funded By | KIIFB |
Project Outlay(crores) | 30.93 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 2 % | ||
Current status | DPR was approved by KIIFB on 18.03.2019 for an amount of Rs.30.93 Cr. LA requisition submitted on 04.10.2019. AS for LA GO(Rt) No 3108/2019/RD dt.30.10.2019. GAD approved by Railways on 22.09.2023. Request letter for NOC submitted to Regional Officer, NHAI, TVM on 04.05.2022. Reminder request submitted to Regional Officer, NHAI, TVM on 13.07.2022, 04.07.2023 & 23.11.2023. |