Koduvayur Bypass

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 15
District Palakkad
LAC Nenmara
Project Details
Actual Start Date 16.01.2019
Project Management Consultant KITCO Ltd
Category Road Projects
Length 4.92 km
Right of way 12 m
No of Lanes 2
Financial Details
AS Amount(crores) 15
Funded By KIIFB
Project Outlay(crores) 38.2
Work Progress Details
Physical progress 10 %
Current status LA requisition submitted to District Collector, Palakkad on 15.01.2019. Stone planting completed on 26.02.2020. After conducting the Preliminary survey, LAO requested to correct the survey numbers and block numbers in the requisition and area list. Accordingly revised requisition and corrected area list send to District Collector on 06.02.2021 and requested to Government for amending the land acquisition Government Order. As per G.O(P)No.129/2022/RD Tvm dated 11.04.2022, time for 11(1) notification period extended for one year from expiry date of 30.10.2021. District Collector requested to re-plant the missing stones for LA works. Stone planting work was completed on 06.04.2022 and joint inspection was conducted on 27.04.2022. SIA study completed for missing survey numbers and public hearing completed. SIA report submitted to DC on 28.07.2022. 11(1) notification published on 30.09.2022. Fund request for LA was received on 16/09/2023 and the same was returned by KIIFB directing to submit DVS. DVS received.