Projects

Kuruppanthara ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No. 942/2017/PWD 10.07.2017 33
District Kottayam
LAC Kaduthuruthy
Project Details
Actual Start Date 12.07.2018
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 22
Railway (km) 41/100-200
Length Including Approaches 393.76
Width of ROB 10.15
GAD Status Approved
No of Lanes 2
Financial Details
AS Amount(crores) 33
Funded By KIIFB
Project Outlay(crores) 30.56
Work Progress Details
Physical progress 65 %
Current status DPR approved on 22.05.2018 for an amount of Rs.30.56 Cr. LA requisition submitted on 12.07.2018. 11(1) notification published on 16.07.2020. LA fund request was received from LAO on 11.03.2022 and uploaded in KIIFB portal. KIIFB directed to limit the 12% increase to 6 months and the revised proceeding uploaded to KIIFB portal on 30.03.2022. Revised LA fund request received from the LAO on 18.03.2022 and fund released on 08.04.2022. Requisition for acquiring additional land as per Railway's direction was submitted to DC, Kottayam on 23.04.2022. Stone planting completed on 07.05.2022. Joint site inspection with Special Tahsildar conducted on 08.06.2022. 19(1) declaration published on 14.07.2022. DVS approved by DC. Request for balance cost of Rs. 10,81,655/- submitted to KIIFB on 22.10.2022. Fund received from KIIFB and released to LAO. 61/68 cases award passed. GAD approved by Railways on 02.03.2023. Meanwhile, WP(C) No. 18680 of 2021 filed by K.J James and others challenging the 11(1) notification and entire land acquisition proceedings. The Hon'ble High court had passed an interim order on 13.10.2021 in which a direction was issued to Indian Railways not to take any further action without orders from this court. Award passed for 61 cases out of 68. Remaining cases pending due to WP(C) 18680/2021.