Melechovva Flyover

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 30
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.161/2023/PWD 16.02.2023 28.68
District Kannur
LAC Kannur
Project Details
LA status
Project Management Consultant KITCO Ltd
Category Flyover
Length including approaches 418.39 m
Width of Flyover 10 m (Overall 24 m)
No of Lanes 2 Lane with service road on both side
Financial Details
AS Amount(crores) 30
Revised AS Amount(crores) 28.68
Funded By KIIFB
Project Outlay(crores) 27.59
Work Progress Details
Current status TS committee was held on 29.01.2024 and recommended to issue technical sanction for the estimate amounting to Rs. 31,98,58,890.41. Estimate submitted to KIIFB for sub-project revision on 31.01.2024. KIIFB returned the same by enquiring detailed comparision report. Detailed comparison report was submitted to KIIFB On 20/02/2024. Work tendered on 23/02/2024.