Current status |
LA requisition submitted to District Collector, Thiruvananthapuram on 13.07.2017 and modified LA requisition submitted on 29.08.2018. 11(1) notification published on 28.11.2019. WP(C) 28008/2020 was filed by 12 petitioners against the alignment. 19(1) published on 16.11.2021. BVR approved on 20.01.2022.
GAD approved by Railways on 15.12.2022. On 02.12.2022 Hon'ble High court stayed taking possession of 12 petitioners of WP(c) 28008/2020. Award passed for 69/69 cases as on 05.06.2023. Land possession is progressing. Taking possession of 51/69 completed on 27.05.2023. Instruction given to standing counsel to dispose the case. For 5 cases LAO has requested additional fund and the same was sanctioned on 10.07.2023. The case was disposed on 12/02/2024 and action to be taken by Deputy Collector." |