General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt) No. 1324/2016/PWD | 27.09.2016 | 25 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/T 301/TS-14/2021-22 | 18.10.2021 | 29.5 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.696/2017/PWD | 24.05.2017 | 40.44 | |
District | Kollam | ||
LAC | Karunagapally | ||
Location |
Project Details | |
---|---|
Actual Start Date | 04.01.2021 |
Contractor(s) | M/s SPL Infrastructure Pvt. Ltd |
Project Management Consultant | RITES |
Category | Road Over Bridges |
LC No | 55 |
Railway (km) | 129/547 |
Length Including Approaches | 546.33 |
Width of ROB | 10.15 |
GAD Status | APPROVED |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 25 |
Revised AS Amount(crores) | 40.44 |
Funded By | KIIFB |
Project Outlay(crores) | 35.8 |
TS Amount(crores) | 29.5 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T301/ROB/14 | 25.06.2020 | 222.7 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
RBDCK/ROB/T44/28/2021 | 04.01.2021 | 251.48 | 12 Months |
Work Progress Details | |||
---|---|---|---|
Physical progress | 75 % | ||
Current status | All Foundation, substructure works and superstructure works upto deck slab completed. 95% of Retaining wall works completed. Crash barrier, embankment, Handrail, drainage & service road works are in progress. Railway Portion – Pile, Pile cap, pier, pier cap and Girder erection completed. Deck Slab, Parapet and crash barrier works in progress. |