Eravipuram ROB

Back View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 20
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 301/TS-22/2021-22 03.11.2021 24.51
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.132/2017/PWD 04.02.2017 40.49
District Kollam
LAC Eravipuram
Location
Project Details
Actual Start Date 04.01.2021
Contractor(s) M/s SPL Infrastructure Pvt. Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 547
Railway (km) 159/800-900
Length Including Approaches 411.27
Width of ROB 10.05
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 20
Revised AS Amount(crores) 40.49
Funded By KIIFB
Project Outlay(crores) 31.6
TS Amount(crores) 24.51
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T301/ROB/14 25.06.2020 222.7
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/ROB/T44/28/2021 04.01.2021 251.48 12 Months
Work Progress Details
Physical progress 35 %
Current status All Foundation and substructure completed up to Pier cap (excluding railway portion). Girder erection of 8/10 span completed. Girder erection completed except adjacent span. Deck slabs works in progress. A2 RHS retaining wall completed. A1 RHS retaining wall works in progress. A1 &A2 LHS retaining wall, Drain, service road can be done only after railway girder erection. Railway Portion - All the works are executed directly by Railways. Pile, Pile cap and pier completed. 2/4 pier cap completed.