Projects

CUSAT Package 3 (Electrical)

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No. 807/2017/H.Edn 29.04.2017 240.9
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T220/TS-04/2020-21 12.02.2021 21.46
District Ernakulam
LAC Kalamassery
Project Details
Contractor(s) M/s Seimens Ltd
Project Management Consultant KITCO Ltd
Category Building Projects
Type Electrical Substation
Description Upgradation of Electrical System110KV
Financial Details
AS Amount(crores) 240.9
Funded By KIIFB
Project Outlay(crores) 21.16
TS Amount(crores) 21.46
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/T220/ CUSAT/ PACKAGE III/50/2020 13.02.2021 16.1
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/T220/CUSAT/PackageIII/46/2021 24.12.2021 15.95 03.01.2022 15 months 03.04.2023
Work Progress Details
Physical progress 70 %
Current status Work is divided into 2 parts. One part is the laying of 110 KV line from Kalamassery Substation to CUSAT. This will be executed as deposit work by KSEB. KSEB had submitted the estimate and an amount of Rs. 409.54 Lakhs has been deposited to KSEB. Second part is the construction of 110KV Substation. Agreement was executed with M/s SIEMENS Ltd. on 24.12.2021 and NTP was issued on 03.01.2022. Duration of the project is 15 months. 85% of the total work completed.