Current status |
Entrusted to RBDCK on 03.02.2020. For the preparation of DPR, LOA issued to M/s Velocity on 15.09.2020. Alignment Finalised. Draft DPR submitted by consultant and returned for correction.
Project was pending due to Semi High Speed Rail project of KRDCL. On 06.12.2022, KRDCL had informed to go ahead with the construction of ROBs without considering the silver line alignment and RBDCK intimated the same to Railways on 08.12.2022. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023.