Current status |
DPR approved by KIIFB on 07.09.2021 for an amount of Rs.31.97 Cr. LA to be taken up after getting approval of GAD from railways. Final GAD submitted to railways on 15.03.2022. Reminder letter for approval of GADs submitted to Chief Administrative Officer, Southern Railway, Ernakulam and Chief Engineer (RSW), Sothern Railway, Chennai on 30.06.2022. Railways returned the GAD for incorporating some corrections and revised GAD submitted to Railways on 30.01.2023.
GAD approved by Railways on 10/11/2023.
LA requisition submitted on 23.01.2024 and Revenue (B) sanction awarded on 11/03/2024. 6(1) notification published on 16/03/2024. |