Projects

Nellayi Gate ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Thrissur
LAC Puthukkad
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 32
Railway (km) 50/100-200
Length Including Approaches 473.61 m
Width of ROB 10.20
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 32.35
Work Progress Details
Physical progress 60 %
Current status DPR approved by KIIFB on 04.09.2021. LA to be taken up after getting approval of GAD from railways. Final GAD submitted to Railways on 17.02.2022. Reminder letter for approval of GADs submitted to Chief Administrative Officer, Southern Railway, Ernakulam and Chief Engineer (RSW), Sothern Railway, Chennai on 30.06.2022. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line. Joint Site inspection held on 10/10/2023 along with Railways. Awaiting NOC from Railways.