Projects

Manjeshwar ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Kasargod
LAC Manjeshwaram
Location
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 291
Railway (km) 868/800-900
Length Including Approaches 480.30
Width of ROB 10.20 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 40.4
Work Progress Details
Physical progress 74 %
Current status DPR approved by KIIFB on 09.08.2020 for an amount of Rs.40.40 Cr. LA plan under preparation. The requisition will be submitted to District Collector after the approval of GAD from Railways. A joint site inspection was carried out with NHAI and ULCCS representative on 18.10.2021 at Manjeshwar. On 20.10.2021 NHAI sent a letter and requested to modify the alignment. Accordingly, RBDCK directed consultant M/s ISA to revise the drawing of Manjeshwar ROB on 05.11.2021. But, consultant M/s ISA informed that they required both vertical and horizontal alignments of NH project under execution to suit the profile. The details are collected from NHAI and based on the same GAD was modified and submitted to NHAI and Railways for concurrence on 07- 05-2022. Vide letter dated 26.05.2022, Railways informed that the GAD found ok. Reminders for getting Concurrence were submitted to NHAI on 22.07.2022 and 18.11.2022. On 30.11.2022 Sr. Project Manager ULCCS informed that they have verified the GAD forwarded by RBDCK and found that it is not obstructing / intervening, the approved alignment of NH66 and we can proceed further. Final GAD submitted to railways for approval on 12.01.2023. Reminder submitted to Railways on 03.07.2023.