Projects

Uttara ROB And River Bridge

Back View Alignment

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No. 942/2017/PWD 10.07.2017 20
District Palakkad
LAC Nenmara
Location
Project Details
Actual Start Date 16.12.2020
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 33
Railway (km) 35/600-700
Length Including Approaches 447.371m
Width of ROB 10.20 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 20
Funded By KIIFB
Project Outlay(crores) 10.61
Work Progress Details
Physical progress 10 %
Current status DPR approved by KIIFB on 11.02.2020 for an amount of Rs.10.61 Cr (for river bridge and LA of ROB only). LA requisition submitted to District Collector, Palakkad on 16.12.2020. Revenue (B) sanction obtained as per G.O.(Rt) No.282/2021/RD dated 27.01.2021. Boundary stone planting completed and joint site inspection was conducted on 28.06.2021. As contignecy charge advance, Rs. 3,00,000/- released to LAO on 02.07.2021. 4(1) Notification published on 11.10.2021. Contingency fund Rs. 10,67,415/- released to LAO on 26.11.2021. SIA public hearing was conducted on 20.12.2021. Expert committee meeting conducted on 07.02.2022 and report submitted to DC. 11(1) notification published on 18.06.2022. LA cost of Rs. 7,79,94,317/- released to LAO. 19(1) published on 15.06.2023. Regarding the construction of River Bridge only 5.13 Ares of land is required to be acquired from 2 stake holders and we had already received the advance procession certificate from both the stakeholders. Accordingly, we had revised the estimate and requested KIIFB for granting permission to tender the work vide letter dated 06.09.2022. Vide dated 28.12.2022 KIIFB had given permission to go ahead with the tendering process. Generally bridge portion is tendering as Lump sum mode and the design has prepared by the Contractor after award of the work. But vide G.O.(Ms) No. 34/2022/PWD dated 02.12.2022 Government had directed to follow G.O.(P) No 30/2016/Fin dated 29.2.2016 which stipulates item rate tender for all future work. Since this is a small work, we had instructed the PMC M/s RITES on 04.01.2023 to prepare and submit the design drawings for tender the work as item rate. The design submitted to IIT for vetting on 08.08.2023. Design and drawings approved by IIT and the same with revised estimate was submitted to TS committe on 27/12/2023. Estimate was returned with comments on 29.01.2024 and the same resubmitted on 05.02.2024. TS for construction ussued on 08.02.2024 and submitted to KIIFB for approval. After several revisions Railways directed to submit the GAD to CBE Chennai as this is a deposit work. Also, Railways directed to submit the GAD along with the joint feasibility report. Joint Feasibility report was submitted to ADEN, Palakkad for signature on 06.04.2022. Revised GAD was submitted to Railways on 13.06.2022. Land possession is in final stage.