Weekly Progress report of Eroor ROB as on 11-03- 2017
 
1.Stair Case palarivattoom End- Completed
2.Drain at Palarivattom service Road-120 mtr Completed (Balance remaining- 45 mtr)

3.Paver block laying in progress at tripunithura side.

 