Weekly Reports

Airport- Seaport Road – Phase II (Section B) Two Bridges across Periyar from Mahilalayam to chowara

Graph Project Graph

Weekly Progress of Mahilalayam Small Bridge as on 25-02-2017
 

Sl.No.

Item Description

Unit

Planned Qty

Executed Qty

Work completed (%)

Remarks

1

GSB at Chowara side

1

220

220

100

 

 

2

Median works

3

1

1

33

 

 

 

 

 

 

 

 

 

 

Works during this week

1)      Chowara side approach GSB leveling and compaction.

2)      Deck slab cleaning for mastic works.       

3)      Median works at Aluva-Perumbavoor road intersection.

 

Works proposed for next week               

1)      GSB works final levels and reporting to CT.

2)      Aluva - Perumabavoor road median works.

3)      Mahilalayam side sub grade filling.

4)      Dismantling of labour shed(building).

 
Click here to view Previous Reports
 
    
MEDIAN SHUTTERING

    
    
GSB LAYING

    
    
DECK SLAB CLEANING

    
    
CHOWARA SIDE GSB LAYER

    
 
 

 

 

 

 

 

 

 