Edappal Flyover

Graph Project Graph |Photo gallery Photo Album

Weekly Progress Report - 27.07.2020 to 01.08.2020
 
Weekly Progress Report - 27.07.2020 to 01.08.2020
27.07.2020 28.07.2020 29.07.2020 30.07.2020 31.07.2020 01.08.2020
Reinforcement binding for girders at first span and between P6-P7 span. Reinforcement binding for girders at first span and between P6-P7 span. Reinforcemet works at first span at Thrissur side in progress. Reinforcement Bending and Cutting Work No works at site Reinforcement Bending and Cutting Work
    Cable profiling at Kuttipuram side in progress. No major works due to rain.   No major works due to rain.
           
           
           




 

 
Click here to view Previous Reports
 
    
REINFORCEMENT BENDING WORK

    
    
CABLE PROFILING WORK

    
    
REINFORCEMENT WORK

    
    
REINFORCEMENT WORK

    
    
REINFORCEMENT BENDING & CUTTING

    
    
CURING

      
 

 

 

 

 

 

 

 