Weekly Progress of Station Kadavu River Bridges (Balance work) as on 08-07-2017
 

Sl.No.

Item Description

Unit

Estimated Qty

Executed Qty

Work completed (%)

Remarks

1

Pile

nos

49

 

49

 

100.00 %

 

 

2

Pile cap

nos

8

8

      100.00 %

 

 

3

Pier

nos

 

7

 

 

7

 

        100 %

 

4

Pier cap

nos

 

9

 

9

 

100.00 %

 

 

5

 Girder 

nos

34

23

         67.64 %

 

6

Deck Slab

nos

11

5

45.45 %

 

 

Works during this week

P9-P10 Hand Rail portion (Horizontal) Concreted.

P2-P3 RHS I Girder Prestressed & Grouted.

Works proposed for next week

I Girder                                      :  P2-P3

Retaining  Wall    LHS             :    A2

 
Click here to view Previous Reports
 
    
P2-P3 CENTRE I GIRDER CURING

    
    
P2-P3 CENTRE I GIRDER CURING

    
    
N TRUSS SHIFTING

    
    
RETAINING WALL REINFORCEMENT TYING

    
    
RETURN WALL BRACKET CURING

    
    
HAND RAIL PORTION

      
 

 

 

 

 

 

 

 