Stationkadavu-Valiapazhampillithuruthu River Bridge

Graph Project Graph

Weekly Progress of Station Kadavu River Bridges (Balance work) as on 23-11-2017
 

Sl.No.

Item Description

Unit

Estimated Qty

Executed Qty

Work completed (%)

Remarks

1

Pile

Nos

49

 

49

 

100.00 %

 

 

2

Pile cap

Nos

8

8

      100.00 %

 

 

3

Pier

Nos

 

7

 

 

7

 

        100 %

 

4

Pier cap

Nos

 

9

 

9

 

100.00 %

 

 

5

 Girder 

Nos

34

33

   94.120  %

 

6

Deck Slab

Nos

11

9

63.63 %

 

 

Works during this week

P5-P6 Centre – RHS  - I Girder Prestressed.

A1-P1  Deck slab Concreted.

P3-P4  Deck Slab Concreted.

Works proposed for next week

I Girder     P5-P6             : 1 No

 
Click here to view Previous Reports
 
    
P5 DIAPHRAGM CURING

    
    
P5-P6 CENTRE-RHS I GIRDER CURING

    
    
A1-P1 DECK SLAB REINFORCEMENT

    
    
P3-P4 DECK SLAB CURING

    
 
 

 

 

 

 

 

 

 