Weekly Progress of Station Kadavu River Bridges as on 10-04-2017
 

Sl.No.

Item Description

Unit

Estimated Qty

Executed Qty

Work completed (%)

Remarks

1

Pile

nos

49

 

49

 

100.00 %

 

 

2

Pile cap

nos

8

8

      100.00 %

 

 

3

Pier

nos

 

7

 

 

7

 

        100 %

 

4

Pier cap

nos

 

9

 

9

 

100.00%

 

 

5

 Girder 

nos

34

17

         50.0%

 

6

Deck Slab

nos

11

1

0.090%

 

 

Works during this week

A1-P1  LHS  I Girder Prestressed  .

P7-P8 LHS  I Girder Prestressed.

A1-P1  RHS  I Girder Grouted.

Works proposed for next week

  I Girder concrete                                                       : 1 No 

  Deck  Slab                P10-A2     Span                        : 1 No

 