Stationkadavu-Valiapazhampillithuruthu River Bridge

Graph Project Graph

Weekly Progress of Station Kadavu River Bridges as on 11-03-2017
 

Sl.No.

Item Description

Unit

Estimated Qty

Executed Qty

Work completed (%)

Remarks

1

Pile

nos

49

 

49

 

100.00 %

 

 

2

Pile cap

nos

8

8

      100.00 %

 

 

3

Pier

nos

 

7

 

 

7

 

        100 %

 

4

Pier cap

nos

 

9

 

9

 

100.00%

 

 

5

 Girder 

nos

34

13

         38.23%

 

6

Deck Slab

nos

11

0

0.0%

 

 

Works during this week

P9-P10 Diaphragm Concreted .

P7-P8 I Girder works.

A1- P1 ,outer  I Girder  Concreted

A1- P1 ,centre  I Girder  works.

Works proposed for next week

  I Girder concrete      (P1-A1)                                   : 1 No 

  I Girder concrete      (P7-P8)                                   : 1 No

  Slab P9-P10     Span

 
Click here to view Previous Reports
 
    
P7-P8 I GIRDER REINFORCEMENT TYING

    
    
P9-P10 SPAN DIAPHRAGM CONCRETING

    
    
A1-P1 I GIRDER

    
    
P3 PIER CAP CURING

    
 
 

 

 

 

 

 

 

 