Weekly progress report of Thirunettur ROB as on 04.02.17
 
Sl No. Item Description Estimated Qty Executed Qty Upto JANUARY 2016 Works During february Executed Qty Upto february Balance Qty Details of completed items. Remarks
Planned Executed
1 PILE 28 12 0 0 12 16 A2-1/2/3 , P7-1/2/3, P6-1,2,3 , P5-1,2,3  
2 LOAD TEST 1 1 0 0 1 0    
3 PILECAP 9 4 0 0 4 5 A2,P7,P6,P5  
4 PIER 9 4 0 0 4 5 A2,P7,P6,P5  
5 PIERCAP 7 3 0 0 3 4 p7,p6,p5  
6 PEDESTAL 32 10 4 4 14 18 A2,P7,P6,P5  
7 RETAINING WALL 68.7 0 0 0 0 69    
8 EARTH EMBANKMENT 77.82 0 0 0 0 78    
9 GIRDER 7 1 1 0 1 6 a2-p7  
10 GIRDER ADJ SPAN 2 0 0 0 0 2    
11 DECK SLAB 7 1 1 0 1 6 A2-P7  
12 DECK SLAB ADJ. 2 0 0 0 0 2    
13 EXPANSION JOINT 9 0 0 0 0 9    
14 HANDRAILS   0 0 0 0 0    
15 KERB 572 0 48 48 48 524 A2-P7  
16 ROAD WORK   0 0 0 0 0    
17 DRAINAGE   0 0 0 0 0    
18 HANDRAIL FIXING   0 0 0 0 0    
 
Click here to view Previous Reports
 
 
 

 

 

 

 

 

 

 